As part of the project to improve the water and communal infrastructure of the Agglomeration Zadar - Petrčane, 24.04.2023. the Contract for the last activity was signed.
The mentioned activity will include the construction of the drainage system of the catchment area of Put Bokanjca Street and the settlements of Kožino and Petrčane, the reconstruction of the water supply system and the construction of the connecting pipeline Petrčane - Kožino - Žmirići intersection, which in numbers means the construction of a total of:
• 33.5 km of gravity pipelines
• 15 km of water supply pipelines
• 6.6 km of pressure pipelines
• 3.6 km of storm drainage
• 8 pumping stations
• 1480 preparations for home connections